The Floating Storage Regasification Unit (FSRU) vessel LNG CROATIA has arrived on the location of the Krk terminal, where it was successfully moored in the special purpose port of the terminal.
In accordance with the planned project activities, all activities related to the commissioning of the terminal have already begun on 2 of December 2020: the testing of certain systems of the FSRU vessel and the testing of the onshore facilities, all in order for the terminal to start commercial operations on 1st of January 2021.
Earlier in November, the FSRU had left Viktor Lenac shipyard, departying for Spain, from the port of Sagunto.